Importance of Being on Time Essay Examples

Time Crash Time Normal Cost Crash Cost Predecessor Max red NT-CT Cost to Crash per period CC-NC A 10 8 50 150 10-8=2 150-50=100 B 4 2 40 200 4-2=2 200-40=160 C 7 6 70 160 B 7-6=1 160-70=90 D 2 1 20 50 A,C 2-1=1 50-20=30 E 3 3 30 30 A,C 3-3=0 30-30=0 F 8 5 80 290 B 8-5=3 290-80=210 G 5 4 50 180 D 5-4=1 180-50=130 H 6 3 60 180 E,F 6-3=3 180-60=120 CC-NC/NT-CT(COST TO Crash Per Period) 150-50/10-8= 100/2=50 200-40/4-2=160/2=80 160-70/7-6=90/1=90 50-20/2-1=30/1=30 30-30/3-3=0 290-80/8-5=210/3=70 180-50/5-4=30/1=30 180-60/6-3=120/3=40 Project cost without crashing is 13 days(add the sum of Max Red) Normal cost is 400 Crash cost is 1040 Production cost is 400 Duration 45 days(sum of...